Use the online service to submit your application:
- Call up the federal government's online service "Application and participation portal for transport and offshore projects".
- If you are registering there for the first time: Register as a project sponsor.
- Then log in with the ELSTER company account using your ELSTER certificate.
- The form management system (FMS) will guide you step by step through the required information. Complete the application form in full.
- Upload the required documents as a PDF file and submit the application. You will receive an automatic confirmation of receipt.
- The FBA will check your documents and may contact you if you need to submit additional documents.
- The FBA will send you a notification in which it informs you of the decision on the approval under planning law.
The application is part of the planning approval procedure. The general procedure is as follows:
Preliminary consultation:
- As the project developer, application consultations take place between you and the FBA.
Application:
- Submit an application for the plan approval procedure via the federal government's online service and submit all the necessary documents there.
Hearing procedure:
- Once you have submitted all the documents in full, the hearing procedure is initiated. This means that public bodies are invited to comment. The public can now submit any concerns or suggestions for changes.
Announcement of the publication of the plan:
- The FBA arranges for the plan to be made public. This is not only done in the "Application and Participation Portal for Transport and Offshore Projects", but also in local daily newspapers in whose circulation area the project is likely to have an impact.
Publication of the plan:
- The plan is published in the "Application and Participation Portal for Transport and Offshore Projects" so that interested parties can view it.
Submission of objections and comments:
- Objections and comments are submitted as part of the public participation process. The public involved includes those affected by the project as well as recognized environmental and nature conservation associations.
Response by the project developer:
- If there is a hearing procedure, you must respond to the objections received and comments submitted as part of the public and authority participation.
Hearing date:
- The FBA decides on the basis of the objections and comments whether a hearing is necessary.
- If a hearing is held, the objections and comments received in good time are discussed together with the project sponsor, the public agencies, the affected parties and the recognized associations.
Plan amendments to the planning approval procedure:
- Plan amendments may be made as a result. All persons affected by the changes are informed.
- In the event of extensive changes to the plan, the consultation procedure must be repeated.
Planning approval decision:
- The planning approval authority weighs up all the concerns and takes them into account in the planning approval decision.
- As the project developer, you will be subject to conditions.
Publication of the planning approval decision:
- The planning approval decision is announced to the parties involved in the proceedings.
Legal action:
- An action can be filed against a planning approval decision.
- Final plan:
- If no one files a lawsuit against the planning approval decision, your plans become binding and you can begin construction.
Final plan:
- If no one files an action against the planning approval decision, your plans become binding and you can start construction.