Ensuring operational safety - apply for a permit to set up and operate petrol stations
Source: BUS Rheinland-PfalzPetrol stations are fixed installations that refuel land, sea and air vehicles with flammable liquids. They are systems that need to be monitored.
You will need permission from the competent authority if you:
- want to build and operate a petrol station
- want to make changes to the design or operation that affect the safety of the installation.
Permission can be granted to you subject to the following restrictions:
- limited
- temporary
- under conditions, or
- with conditions.
If the installation requiring a permit is part of an installation requiring a permit, no separate permit will be issued. The permit includes the permission.
- Submit the application for permission for the installation requiring monitoring to the competent authority with the necessary documents, including the test report of the approved inspection body (ZÜS).
- If there is a permit requirement under the Federal Immission Control Act, you will receive the application documents back, as a permit under the Industrial Safety Ordinance will then be checked as part of the necessary permit under the Federal Immission Control Act.
- The competent authority shall take its decision after examination and shall inform you thereof.
The competent authorities in Rhineland-Palatinate are the Labour Supervision Departments of the Structural and Licensing Authorities North and South.
Regional Offices Trade Inspectorate of the Structure and Approval Directorate North (SGD North) or South (SGD South)
- The plant for which you are applying for the permit must be an installation requiring a permit.
- You must build and operate a state-of-the-art filling station.
- Your documentation must be complete, plausible and meaningful.
- The test report of the approved inspection body (ZÜS) must confirm that the requested installation can be operated safely if the measures specified in the documents, including the tests, are complied with.
Informal application with the following information:
- Last name, first name, company name
- Address of the applicant
- Contact information (e-mail, telephone number, fax)
- Type of permission:
- Construction and operation
- modification and operation, or
- Partial permission
- Indication of the place of operation
Documents to be able to assess the plant:
- Subject matter of the application
- Description of the plant
- Description of the plant technology and interaction with other plants, e.g. car washes
- Piping and instrumentation diagram (P&ID diagram)
- Safety Data Sheets
- Description of the mode of operation
- Permanent position in the case of unsupervised operation
- Lay-out
- Site plan
- Floor plan or technical plan
- Ex zone plan
- Explosion protection concept
- Information on fire protection
- Description of liquid-tight roadway with drainage and effective areas
- Calculation of manufacturing costs
- Other installations
- Test report of an approved inspection body (ZÜS)
- The test report must confirm that the system can be operated safely if the above measures are observed.
- file number and indication of the approval authority of a building permit that has already been issued, or
- Indication of the approval authority in the case of a building permit that has yet to be applied for or has already been applied for
Fee: 160,00 - 20000,00 EURPayment in advance: nohttps://www.landesrecht.rlp.de/bsrp/document/jlr-ArbSchGebVRP2009rahmen
A granted permit expires if:
- you have not started the construction of the installation within two years of the permit being granted,
- you have interrupted the construction of the installation for two years or more, or
- You have not operated the system for a period of three years.
For important reasons, you can apply to the licensing authority for an extension of the deadlines.
The processing time applies from the date of receipt of the complete application documents. An extension of the processing time is possible in justified cases.
Processing Time: 0 - 3 Months
Contradiction:
- You may appeal against the decision within one month of notification.
- You must submit the objection to the competent authority in writing or for a record.
- In Rhineland-Palatinate, objections can also be filed in electronic form.
Forms available: No
Written form required: Yes
Informal application possible: Yes
Personal appearance required: No
Online services available: No
The publication (LV 49) contains a list of the required application documents for petrol stations in Annex 6.
The permit of the SGD North or South does not include the building permit. This must be applied for separately